Guemes Channel Trail Phases I and VII - Edwards Way to Lovric's Shipyard

Status: Completed July 2015

Length: 6,200 Feet

Cost: $990,000

This portion of the trail was done in three sections.  One was completely funded and build by an adjacent development (San Juan Passage) one was done cooperatively with the City of Anacortes and developers and the third section was done with an appropriation from the State Capital Budget.  It was the first section of the Guemes Channel Trail to be completed and has been very popular even though it is a short out and back type trail.  This section was funded through a Washington State Department of Transportation Bike / Pedestrian Grant, Developer Funds, City Funds and the State Capital Budget.