2023 Asphalt Overlay Project

Overview

The City of Anacortes Public Works Department is moving forward with the 2023 Asphalt Overlay Project in the Skyline area for the following streets (also see map below):

  • Skyline Way (from Sunset Avenue to Kingsway)
  • Sands Way
  • Parkside Drive
  • Leah Place
  • Curtis Court
  • Sandra Court
Overlay 2023

Schedule

This project is tentatively scheduled to begin in early June. Some of the work is weather dependent and the schedule may change. There will be days of no parking on the streets; there may be temporary road closures and detours; and there will be traffic delays to allow for the work.

The work on this project includes:

  • Pavement grinding
  • Pavement repairs
  • Asphalt pre-leveling
  • Asphalt overlay
  • Painting, stop bars, fog lines, and bicycle symbols

The work will typically take place from 7 am to 7 pm Monday through Friday, although construction may be allowed during weekends if necessary. During construction there will be traffic control allowing for resident access, but expect possible delays to allow the contractor to perform the work safely.